Proper installation of the KTI PS 803 Plastic / ABPS Wheel Stopper (SKU: KTI16032001P803) ensures effective vehicle overrun prevention, structural stability, and reliable perimeter protection across commercial and industrial parking facilities. Engineered with dimensions of 500 mm length, 150 mm width, and 100 mm height at a unit weight of 1.6 kg, this wheel stop must be securely fixed directly into the ground or pavement surface to handle repeated tire contact from standard cars and utility vehicles.
Pre-Installation Layout and Slot Positioning
Before drilling, facility managers and installation contractors must establish the exact tire contact line within each individual parking bay. Proper positioning prevents vehicle overhang from damaging walls, curbs, pedestrian walkways, or automation barrier hardware.
- Bay Alignment: Position the KTI PS 803 unit perpendicular to the vehicle approach angle at the head of the parking slot.
- Contact Distance: Measure the setback distance from the front barrier or curb so that tire contact with the 100 mm high profile halts the vehicle before bumper contact occurs.
- Surface Check: Verify that the concrete or asphalt ground surface is level, structurally intact, and free from loose debris, standing water, or severe surface fracturing.
Required Equipment and Mounting Preparation
Anchoring the plastic / ABPS structure requires standard industrial installation tools compatible with solid ground and pavement surfaces:
- Industrial rotary hammer drill machine with appropriate diameter masonry bits.
- Heavy-duty mechanical anchor fasteners engineered for ground and pavement anchoring.
- Air blower, wire brush, or vacuum for hole cleaning.
- Socket wrench or impact driver for tightening mounting hardware to full torque.
- Chalk line or measuring tape for multi-bay alignment.
Step-by-Step Direct Surface Anchoring Procedure
Follow these sequential installation steps to secure each 1.6 kg PS 803 module into the designated pavement location:
Step 1: Placement and Hole Marking
Place the 500 mm x 150 mm base of the wheel stopper directly onto the clean pavement at the designated tire stop line. Use a marking pen or drill bit through the pre-formed mounting holes to mark anchoring locations onto the ground.
Step 2: Substrate Drilling
Move the wheel stopper aside. Using the drill machine with a matched masonry drill bit, drill vertical mounting holes into the ground or pavement to the specified depth required by the mounting fasteners.
Step 3: Debris Evacuation
Clear all concrete dust, pulverized aggregate, and loose debris from the drilled holes using compressed air or a cleaning brush to ensure maximum mechanical fastener grip.
Step 4: Fastener Insertion and Torque
Reposition the KTI PS 803 stopper over the drilled holes. Insert the anchoring fasteners through the wheel stopper body into the substrate. Tighten the fasteners firmly using a socket wrench until the ABPS base sits flush against the pavement surface without warping.
Installation Quality and Layout Matrix
| Parameter | Specification / Procedure |
|---|---|
| Product Reference & Model | KTI16032001P803 (Model PS 803) |
| Stopper Dimensions & Weight | 500 mm (L) x 150 mm (W) x 100 mm (H) | 1.6 kg |
| Mounting Substrate | Ground and pavement surfaces (concrete / asphalt) |
| Tool Requirement | Drill machine, masonry drill bit, socket driver |
| Target Application | Outdoor parking lots, perimeter barriers, vehicle roll protection |
Post-Installation Verification
Conduct a visual and mechanical inspection across all installed bays. Verify that the 100 mm height profile remains level, fasteners are fully seated, and the unit does not rock or shift when moderate lateral pressure is applied. Clean the surrounding pavement to complete the traffic safety installation.